On August 7th. Deb, Tim, and I drove to Almanor. The plan was to finish painting the trim and metal vents and to install the DWV piping. Pete Trockey drove up Saturday morning, August 8th, and spent the day installing the majority of the drain waste and vent (DWV). Scott Oswald spent a couple of hours Saturday morning framing the upstairs bathroom walls and Tim got to help put the walls in place. Then Tim and I went back to the Dusty road cabin to finish painting trim. Pete finished the DWV around 5:30pm and then left to go to his cabin near Quincy. Deb, Tim, and I went to the firehouse on Scott drive for a fundraising dinner. Sunday we swept up wood chips and saw dust at the cabin to leave it clean for the carpenter. We put all of the painted trim back in the Dusty road cabin garage and headed for home. We made a lot of progress over the weekend.
On Tuesday night August 11th I drove back up to Almanor to be onsite for a window delivery on Wednesday morning. Windows were delivered at around 8:30am. I helped Scott load some of the painted facia and then drove to Chester to pick up two boxes of galvanized nails. When I returned I primed and painted the 2x6 outrigger material and met with an insulation contractor. I returned to the Dusty road cabin for lunch at 12:30 then called Jennifer at 1:30. Jennifer told me that she will be assigned her post tomorrow. At around 2pm I returned to the cabin to fix the sill height for the master bedroom window (I ordered the wrong height window. The height will be fine). On my way home from Almanor I stopped by Oakridge cabinets in Chico to work out the details on the cabinet bid. On the way home I also checked with Jed regarding sheetrock delivery and with Patrick regarding the timing for metal roofing.
Thursday night, August 13th, I picked up the shower pans and some electrical conduit as I began making plans to install the electric panel.
That’s all for now.
Friday, August 14, 2009
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment