| 8/6/2009 | Talked to the Maze Nail rep and ordered the Maze nails. Talked to Sierra Stair in Loomis and order two newel posts. Jed visited the site today to verify sheetrock and loading. |
| 8/5/2009 | Researched the correct nails for the siding. Researched available newel posts. Asked Scott to verify that he has a gun to shoot the Maze Nails. Met with Jed and gave him a copy of the floor plan for his use in deciding where to stock the sheetrock. Gave Jed a map to jobsite. |
| 08/04/09 | Talked to Jed regarding final details for sheetrock order and stock. |
| 08/03/09 | Trusses arrived at the site at 10:30. They were set in place by 12:00pm. Went back to cabin and put all of the trim back in the garage. |
| 08/02/09 | Cut the painted plywood into 12" strips and delivered them to the jobsite. |
| 08/01/09 | Got up early to go to neighbors cabin (that has the same siding and roof) and look at painted trim samples. It was a hard decision but we chose the colors. Drove to Chico, bought paint, and drove back to Almanor. Set up saw horses and plywood on the ground. Started painting at around 1pm. Stan and Denis showed up and helped with painting the green trim and painting the primer on 12 sheets of plywood. Cleaned up the sprayer and then painted the finish color on the plywood (to be used for the soffits) |
| 07/31/09 | Talked to Scott to make sure that he will be ready for Trusses on Monday. Called Moss Lumber to verify that trusses will arrive Monday morning. Arrived at Almanor at 7pm. Scott is just finishing. He has ridge and some of the rafters set. He had to work alone for the afternoon. Cut 4 pieces of trim and painted several colors so that we can make a choice Saturday morning. |
| 07/30/09 | Bought 4 sample quarts of paint at lunch. Purchased a Graco paint sprayer after work. Watched DVD on how to use paint sprayer late that night. |
| 07/29/09 | Deb doesn't like colors so I will pick some more. |
| 07/28/09 | Erin and I went to Kelly Moore at lunch to look at paint and paint sprayers. Picked some preliminary colors |
| 07/27/09 | Roof Frame package arrived from Meeks in Chico. Fascia and Trim was dropped off at the old cabin for painting next weekend. |
| 07/26/09 | Worked at the old cabin cleaning out the back garage to make room for painting the trim. |
| 07/25/09 | Went to jobsite to count lumber and verify that all of the roof beams were there. Checked out the 2nd floor frame. |
| 07/24/09 | 7am, looked at cultured marble showers and sinks in Martinez. Then drove to work while talking to Dave Shelton at Meeks lumber regarding the roof frame package that will arrive on Monday July 27. Also Talked to Andy Lester regarding the date that windows will arrive. Andy said that the windows will arrive onsite on August 12th. Picked up the wood stove info from Denis Gregerson. |
| 07/23/09 | Scott Oswold called to say that one 20' 6x12 was not shipped. He also said that the rim joist material was not shipped. I asked Scott to recheck the lumber and he found the 5-24' lvl. I talked to Dave Shelton and asked him to add the missing 20' - 6x12 to the Monday roof frame package. I also noted that we need a good 20' 6x10 to replace a twisted one that cannot be used for the front porch. Scott said that he had the first floor framed and plumb & lined. |
| 07/22/09 | Talked to Jed regarding the sheetrock bid. He gave me his price and I said that it is in the ballpark and that I will check out some places for he and his crew to stay during their phase of work. Ordered Roof Frame Package and ordered Trusses |
| 07/21/09 | Ordered Windows. I was told that the windows would ship on August 17th. (Yikes! This is not acceptable) |
| 07/15/09 | Met with Scott Oswold onsite to clarify the location of foundation vents and supports for all point loads. Waited for the inspector for the underfloor inspection and had delivery of the second lumber package. |
| 07/12/09 | Pete Trocky installed the copper water lines in the underfloor. |
| 07/11/09 | Pete Trocky installed the DWV and gas lines underfloor today. Tim and I formed the concrete walls for the water access in the garage. We also cleaned some of the rocks from the underfloor |
| 07/10/09 | Scott installed the first floor joist and girders today |
| 07/08/09 | Foundation was poured today, Wednesday, July 8, 2009 |
| 07/03/09 | Scott has made a lot of progress on setting forms this week. He expects finish the forms on Monday and pour Tuesday |
| 06/29/09 | Scott Oswold began setting forms today. Deb is staying at the cabin all week |
| 06/25/09 | Darren Strand dug the foundation |
| 06/24/09 | Met Darren Strand and Scott Oswold onsite to clarify the details for laying out the foundation and the final height of the foundation. |
| 06/23/09 | Darren Strand cut the rough grade and house pad |
| 06/15/09 | Drove to Quincy to pay for Building Permit. Also stopped by county road department and paid for the encroachment permit |
| 06/05/09 | Bldg Permit Approved |
| 06/01/09 | Septic Permit Approved |
| 05/29/09 | Received lumber bid from Meeks |
| 05/21/09 | Submitted Plans to Plumas Co Env Health Dept |
| 05/21/09 | Provided Plans to Earle Colridge for Lumber Takeoff |
| 05/20/09 | Structural Plans Complete |
| 05/20/09 | Submitted Plans to Plumas Co Bldg Dept |
| 05/18/09 | Provide Comments to Jim MacIntyre |
| 05/15/09 | Received Draft Plans from Jim MacIntyre |
| 04/30/09 | Taylor Metal estimate |
| 04/29/09 | Received Final Plans from Paul Friend |
| 04/21/09 | Preliminary plans to Jim MacIntyre |
| 04/11/09 | Received answer from PG&E re: overhead service |
| 04/10/09 | Received Preliminary Plan from Paul |
| 04/08/09 | Gave Bob's dwg files to Paul Friend |
| 04/07/09 | Received Preliminary Plan from Bob |
| 04/06/09 | Met at Quicy Bldg Dept and Meet with Engineer |
| 03/30/09 | Preliminary Plan to Bob Fessenden |
| 03/26/09 | Signed Loan Papers |
| 03/17/09 | Received Final Papers |
| 03/11/09 | Received Preliminary papers |
| 03/09/09 | Start Refinance for Hillsview Dr |
Very detailed and technical. I want to see more commentary now that you'll be posting more in congruence with the cabin's progress.
ReplyDeletepiiictuures!!! I mostly want to see pictures, mostly. Great blog! I am glad to follow along!
ReplyDelete